What theme estimates the cost of delivering the project?
A. Business Case
B. Change
C. Plans
D. Progress
Answer: C
Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts
Answer: B
PRINCE2-Foundation Questions Dumps
Monday, 10 February 2020
Monday, 30 September 2019
PRINCE2-Foundation Questions Answers
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
A. Configuration Item Record
B. Quality Register
C. Highlight Report
D. Checkpoint Report
Answer: D
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
A. Only corporate or programme management
B. Only the Project Board
C. Only the Project Manager
D. All levels of management
Answer: D
A. Configuration Item Record
B. Quality Register
C. Highlight Report
D. Checkpoint Report
Answer: D
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
A. Only corporate or programme management
B. Only the Project Board
C. Only the Project Manager
D. All levels of management
Answer: D
Friday, 28 December 2018
PRINCE2-Foundation Questions Answers
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
A. project cost tolerance
B. stage cost tolerance
C. Work Package cost tolerance
D. product cost tolerance
Answer: C
Which is a true statement about time-driven controls?
A. Time-driven controls are used for monitoring the progress of Work Packages and management stages
B. Time-driven controls take place when specific events happen
C. Time-driven controls are produced at the end of a stage
D. An Exception Report is a time-driven control
Answer: A
A. project cost tolerance
B. stage cost tolerance
C. Work Package cost tolerance
D. product cost tolerance
Answer: C
Which is a true statement about time-driven controls?
A. Time-driven controls are used for monitoring the progress of Work Packages and management stages
B. Time-driven controls take place when specific events happen
C. Time-driven controls are produced at the end of a stage
D. An Exception Report is a time-driven control
Answer: A
Tuesday, 14 August 2018
PRINCE2-Foundation Question Answer
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience
Answer: B
PRINCE2-Foundation Exam Dumps
Which role is responsible for creating Checkpoint Reports?
A. Senior Supplier
B. Team Manager
C. Change Authority
D. Project Support
Answer: B
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience
Answer: B
PRINCE2-Foundation Exam Dumps
Which role is responsible for creating Checkpoint Reports?
A. Senior Supplier
B. Team Manager
C. Change Authority
D. Project Support
Answer: B
Monday, 26 February 2018
PRINCE2-Foundation Question Answer
Which does NOT reflect the PRINCE2 principle of continued business justification?
A. There must be a justifiable reason for starting a project
B. The business justification drives decision making
C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
D. If a project can no longer be justified, it should be stopped
Answer: C
Which characteristic distinguishes a project from regular business operations?
A. Produces benefits
B. Introduces business change
C. Manages stakeholders
D. Incurs cost
Answer: B
A. There must be a justifiable reason for starting a project
B. The business justification drives decision making
C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
D. If a project can no longer be justified, it should be stopped
Answer: C
Which characteristic distinguishes a project from regular business operations?
A. Produces benefits
B. Introduces business change
C. Manages stakeholders
D. Incurs cost
Answer: B
Tuesday, 26 December 2017
PRINCE2-Foundation Question Answer
Which may be funded from a risk budget?
A. Capturing identified threats and opportunities in the Risk Register
B. Specific management responses to a project's threats and opportunities
C. Producing risk summaries for inclusion in Highlight Reports
D. Any remaining open risks after the project has been closed
Answer: B
Who does the Team Manager report to and take direction from?
A. Project Board
B. Project Assurance
C. Project Manager
D. Project Support
Answer: C
A. Capturing identified threats and opportunities in the Risk Register
B. Specific management responses to a project's threats and opportunities
C. Producing risk summaries for inclusion in Highlight Reports
D. Any remaining open risks after the project has been closed
Answer: B
Who does the Team Manager report to and take direction from?
A. Project Board
B. Project Assurance
C. Project Manager
D. Project Support
Answer: C
Thursday, 9 November 2017
PRINCE2-Foundation Question Answer
Which is a purpose of an End Stage Report?
A. Summarize progress to enable the Project Board to decide what action to take next
B. Summarize how the project performed against the version of the Project Initiation Documentation used to authorize it
C. Provide the detailed analysis of a deviation and offer options for the way to proceed
D. Provide a plan for the next stage of the project
Answer: A
A. Summarize progress to enable the Project Board to decide what action to take next
B. Summarize how the project performed against the version of the Project Initiation Documentation used to authorize it
C. Provide the detailed analysis of a deviation and offer options for the way to proceed
D. Provide a plan for the next stage of the project
Answer: A