Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience

Answer: B
                                                                                 PRINCE2-Foundation Exam Dumps

Which role is responsible for creating Checkpoint Reports?

A. Senior Supplier
B. Team Manager
C. Change Authority
D. Project Support

Answer: B