What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
A. Configuration Item Record
B. Quality Register
C. Highlight Report
D. Checkpoint Report
Answer: D
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
A. Only corporate or programme management
B. Only the Project Board
C. Only the Project Manager
D. All levels of management
Answer: D