Which may be funded from a risk budget?

A. Capturing identified threats and opportunities in the Risk Register
B. Specific management responses to a project's threats and opportunities
C. Producing risk summaries for inclusion in Highlight Reports
D. Any remaining open risks after the project has been closed

Answer: B


Who does the Team Manager report to and take direction from?

A. Project Board
B. Project Assurance
C. Project Manager
D. Project Support

Answer: C