What theme estimates the cost of delivering the project?

A. Business Case
B. Change
C. Plans
D. Progress

Answer: C



Which is a task of product-based planning?

A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts

Answer: B