Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
A. Management strategies
B. Plan
C. Stakeholder interests
D. Time-driven controls
Answer: B
What product identifies the management stages and other major control points in a project?
A. Business Case
B. Project Plan
C. Work Package
D. Project Brief
Answer: B