Which is one of the six aspects of project performance that needs to be managed?
A. Progress
B. Change
C. Risk
D. Security
Answer: C
Which is NOT included in the PRINCE2 definition of a project?
A. A project is a temporary organization
B. A project's purpose is to deliver one or more business products
C. A project is part of 'business as usual'
D. A project is based on an agreed Business Case
Answer: C